N04 SDD Progress Ledger
- 2026-09-16T07:58:31Z Plan revision 1 created for mode SDD.
- W1 eligible: T1 -> T2 (serial, no prerequisite).
- W2 blocked on W1: T3 -> T4 -> T5.
- W3 blocked on W2: T6 -> T7 -> T8.
- 2026-09-16T08:10:18Z Task T1: complete (commit
7fe96cc, review W1-T1 PASS, RED->GREEN, 2 tests). - 2026-09-16T08:22:24Z Task T2: complete (commit
ef4a9b8, review W1-T2 PASS, RED->GREEN, 5 tests). - 2026-09-16T08:24:45Z W1 wave review PASS: 7 tests; W1 receipt accepted; W2/T3 eligible.
- 2026-09-16T08:38:07Z Task T3: complete (commit
037ddc7, review W2-T3 PASS, RED->GREEN, 15 tests). - 2026-09-16T08:50:22Z Task T4: complete (commit
7370e51, review W2-T4 PASS, 22 tests; concurrent-create race deferred to T6). - 2026-09-16T09:06:51Z Task T5: complete (commit
a5730a7, review W2-T5 PASS, 22 tests). - 2026-09-16T09:10:27Z W2 wave review PASS: 66 tests; W2 receipt accepted; W3/T6 eligible with concurrency obligations.
- 2026-09-16T09:27:35Z Task T6: failed attempt 1/3 - review W3-T6 FAIL; MySQL REPEATABLE READ concurrent 49->50 limit check can write item 51.
- 2026-09-16T09:40:55Z Task T6: complete after focused repair (commit 97b3b16; W3-T6-rereview PASS; 22 focused tests, 85 onboarding tests).
- 2026-09-16T09:51:11Z Task T7: complete (no commit per instruction; RED->GREEN coverage added; OnboardingEndToEndIntegrationTest 7 tests; 2-review/tag/HIDDEN focused gaps; 96 onboarding tests pass; randomized E2E order pass).
- 2026-09-16T09:51:43Z Execution paused by user for the day. T7 tests complete (96 onboarding tests green); independent T7 review and T8 pending. Manual resume from T7-review only.
- 2026-09-17T01:17:47Z Manual resume accepted. W3 resumes at T7 independent review; T6 remains passed and T8 remains pending.
- 2026-09-17T01:21:54Z Task T7: review W3-T7 PASS; 30 focused tests, 96 onboarding regressions, randomized E2E pass.
- 2026-09-17T09:33:54Z Task T8: documentation implementation complete; after adding missing onboarding assertions, verifier RED was
Missing onboarding path: /onboarding/companies/{companyId}/checklist; static OpenAPI now 135 paths / 172 operations and contains 9 onboarding operations / 6 paths / 20 schemas;python docs/verify_openapi.pyPASS; N04 focused regression PASS (96 tests);mvn clean verifyFAIL (1492 tests, 2 failures, 9 errors) in existing CareerProgress/JobReviewDimension/LocalResumeStorage tests unrelated to T8;mvn -DskipTests packagePASS; no commit; independent T8/W3 review pending.